Minor Works Across Northern Ireland 4 Lots

Minor Works Across Northern Ireland 4 Lots

The competition is for 4 individual lots of mixed refurbishment and small new build works as follows:
Lot: 1 15 Massareene Gardens, Antrim.

UK-Belfast: Houses construction work

2013/S 018-026055

Contract notice

Works

Directive 2004/18/EC

Section I: Contracting authority

I.1)Name, addresses and contact point(s)

Oaklee Homes Group
37-41 May Street
For the attention of: Ross McDonnell
BT1 4DN Belfast
UNITED KINGDOM
Telephone: +44 2890441356
E-mail: developmentprogramme@oaklee.org.uk

Further information can be obtained from: The above mentioned contact point(s)

Specifications and additional documents (including documents for competitive dialogue and a dynamic purchasing system) can be obtained from: The above mentioned contact point(s)

Tenders or requests to participate must be sent to: The above mentioned contact point(s)

I.2)Type of the contracting authority
Body governed by public law
I.3)Main activity
Housing and community amenities
I.4)Contract award on behalf of other contracting authorities
The contracting authority is purchasing on behalf of other contracting authorities: no

Section II: Object of the contract

II.1)Description
II.1.1)Title attributed to the contract by the contracting authority:
Minor Works Across Northern Ireland 4 Lots
II.1.2)Type of contract and location of works, place of delivery or of performance
Works
Main site or location of works, place of delivery or of performance: Northern Ireland.
NUTS code UKN
II.1.3)Information about a public contract, a framework agreement or a dynamic purchasing system (DPS)
The notice involves a public contract
II.1.4)Information on framework agreement
II.1.5)Short description of the contract or purchase(s)
The competition is for 4 individual lots of mixed refurbishment and small new build works as follows:
Lot: 1 15 Massareene Gardens, Antrim.
Construction: Rehabilitation of 1 no. residential bungalow constructed circa 1980’s.
End user: Complex Needs.
Mix: 5 no. 1P/1B units (Up to 25 m² each).
Estimated Construction Cost: GBP 59,000.
Estimated/ Anticipated Start on Site: March 2013.
Estimated/ Anticipated Completion: May/June 2013.
Estimated Construction Period: 3 months.
Contract: NEC3 Short Form.
Lot: 2 Nr Existing Satisfactory Purchases – Canal Street Newry.
Construction –:
(I) We wish to appoint a Contractor to undertake the upgrading works to 1 Nr existing property in Newry to provide 9 Nr. 1P/1B self-contained apartments
End user: Supported Housing – Young adults leaving/left care.
Mix: 9 Nr. 1P/1B Apartments.
Estimated upgrading Cost: Approx GBP 90 k.
Estimated/ Anticipated Start on Site: March 2013.
Estimated/ Anticipated Completion: May 2013.
Estimated Construction Period: 12 weeks.
Lot: 3 Drumalla Park Phase 2, Carnlough.
Construction: 7 General Needs Houses.
End user: General Needs.
Mix: 5 no 5P/3B houses (90/95 m²) and 2 no 3P/2B houses (60/65m²).
Estimated Construction Cost: GBP 620,000.
Estimated/ Anticipated Start on Site: February 2013.
Estimated Construction Period: 9 months.
Lot: 4 L’arche-Ormeau Rd, Belfast Refurbishment/Upgrading Works.
End user: Complex Needs.
Estimated Construction Cost: GBP 90,000.
Estimated/ Anticipated Start on Site: March 2013.
Estimated Construction Period: 2 months.
II.1.6)Common procurement vocabulary (CPV)

45211300, 45211100, 45211000

II.1.7)Information about Government Procurement Agreement (GPA)
The contract is covered by the Government Procurement Agreement (GPA): no
II.1.8)Lots
This contract is divided into lots: yes
Tenders may be submitted for one or more lots
II.1.9)Information about variants
Variants will be accepted: no
II.2)Quantity or scope of the contract
II.2.1)Total quantity or scope:
The competition is for 4 individual lots of mixed refurbishment and small new build works as follows:
Lot: 1 15 Massareene Gardens, Antrim.
Construction: Rehabilitation of 1 no. residential bungalow constructed circa 1980’s.
End user: Complex Needs.
Mix: 5 no. 1P/1B units (Up to 25 m² each).
Estimated Construction Cost: GBP 59,000.
Estimated/ Anticipated Start on Site: March 2013.
Estimated/ Anticipated Completion: May/June 2013.
Estimated Construction Period: 3 months.
Contract: NEC3 Short Form.
Lot: 2 Nr Existing Satisfactory Purchases – Canal Street Newry.
Construction –:
(I) We wish to appoint a Contractor to undertake the upgrading works to 1 Nr existing property in Newry to provide 9 Nr. 1P/1B self-contained apartments.
End user: Supported Housing – Young adults leaving/left care.
Mix: 9 Nr. 1P/1B Apartments.
Estimated upgrading Cost: Approx GBP 90 k.
Estimated/ Anticipated Start on Site: March 2013.
Estimated/ Anticipated Completion: May 2013.
Estimated Construction Period: 12 weeks.
Lot:3 Drumalla Park Phase 2, Carnlough.
Construction: 7 General Needs Houses.
End user: General Needs.
Mix: 5 no 5P/3B houses (90/95 m²) and 2 no 3P/2B houses (60/65 m²).
Estimated Construction Cost: GBP 620,000.
Estimated/ Anticipated Start on Site: February 2013.
Estimated Construction Period: 9 months.
Lot: 4 L’arche-Ormeau Rd, Belfast Refurbishment/Upgrading Works.
End user: Complex Needs.
Estimated Construction Cost: GBP 90,000.
Estimated/ Anticipated Start on Site: March 2013.
Estimated Construction Period: 2 months.
Estimated value excluding VAT: 860 000 GBP
II.2.2)Information about options
Options: no
II.2.3)Information about renewals
This contract is subject to renewal: no
II.3)Duration of the contract or time limit for completion
Duration in months: 4 (from the award of the contract)

Information about lots

Lot No: 1 Lot title: Lot:1 15 Massareene Gardens, Antrim

1)Short description
Construction: Rehabilitation of 1 no. residential bungalow constructed circa 1980’s.
End user: Complex Needs.
Mix: 5no. 1P/1B units (Up to 25m² each).
Estimated Construction Cost: GBP 59,000.
Estimated/ Anticipated Start on Site: March 2013.
Estimated/ Anticipated Completion: May/June 2013.
Estimated Construction Period: 3 months.
Contract: NEC3 Short Form.
2)Common procurement vocabulary (CPV)

45211300, 45211100, 45211000

3)Quantity or scope
Construction: Rehabilitation of 1no. residential bungalow constructed circa 1980’s.
End user: Complex Needs.
Mix: 5no. 1P/1B units (Up to 25 m² each).
Estimated Construction Cost: GBP 59,000.
Estimated/ Anticipated Start on Site: March 2013.
Estimated/ Anticipated Completion: May/June 2013.
Estimated Construction Period: 3 months.
Contract: NEC3 Short Form.
Estimated value excluding VAT: 59 000 GBP
4)Indication about different date for duration of contract or starting/completion
Duration in months: 3 (from the award of the contract)
5)Additional information about lots
Lot No: 2 Lot title: Lot: 2 Nr Existing Satisfactory Purchases – Canal Street Newry
1)Short description
Construction –:
(I) We wish to appoint a Contractor to undertake the upgrading works to 1 Nr existing property in Newry to provide 9 Nr. 1P/1B self-contained apartments.
End user: Supported Housing – Young adults leaving/left care.
Mix: 9 Nr. 1P/1B Apartments.
Estimated upgrading Cost: Approx GBP 90 k.
Estimated/ Anticipated Start on Site: March 2013.
Estimated/ Anticipated Completion: May 2013.
Estimated Construction Period: 12 weeks.
2)Common procurement vocabulary (CPV)

45211300, 45211100, 45211000

3)Quantity or scope
Construction –:
(I) We wish to appoint a Contractor to undertake the upgrading works to 1 Nr existing property in Newry to provide 9 Nr. 1P/1B self-contained apartments.
End user: Supported Housing – Young adults leaving/left care.
Mix: 9 Nr. 1P/1B Apartments.
Estimated upgrading Cost: Approx GBP 90 k.
Estimated/ Anticipated Start on Site: March 2013.
Estimated/ Anticipated Completion: May 2013.
Estimated Construction Period: 12 weeks.
Estimated value excluding VAT: 90 000 GBP
4)Indication about different date for duration of contract or starting/completion
Duration in months: 3 (from the award of the contract)
5)Additional information about lots
Lot No: 3 Lot title: Lot:3 Drumalla Park Phase 2, Carnlough
1)Short description
Construction: 7 General Needs Houses
End user: General Needs
Mix: 5 no 5P/3B houses (90/95 m²) and 2 no 3P/2B houses (60/65 m²).
Estimated Construction Cost: GBP 620,000.
Estimated/ Anticipated Start on Site: March 2013.
Estimated Construction Period: 9 months.
2)Common procurement vocabulary (CPV)

45211300, 45211100, 45211000

3)Quantity or scope
Construction: 7 General Needs Houses.
End user: General Needs.
Mix: 5 no 5P/3B houses (90/95m2) and 2 no 3P/2B houses (60/65 m²).
Estimated Construction Cost: GBP 620,000.
Estimated/ Anticipated Start on Site: March 2013.
Estimated Construction Period: 9 months.
Estimated value excluding VAT: 620 000 GBP
4)Indication about different date for duration of contract or starting/completion
Duration in months: 9 (from the award of the contract)
5)Additional information about lots
Lot No: 4 Lot title: Lot: 4 L’arche-Ormeau Rd, Belfast Refurbishment/Upgrading Works
1)Short description
End user: Complex Needs.
Estimated Construction Cost: GBP 90,000.
Estimated/ Anticipated Start on Site: March 2013.
Estimated Construction Period: 2 months.
2)Common procurement vocabulary (CPV)

45211300, 45211100, 45211000

3)Quantity or scope
End user: Complex Needs.
Estimated Construction Cost: GBP 90,000.
Estimated/ Anticipated Start on Site: March 2013.
Estimated Construction Period: 2 months.
Estimated value excluding VAT: 90 000 GBP
4)Indication about different date for duration of contract or starting/completion
5)Additional information about lots

Section III: Legal, economic, financial and technical information

III.1)Conditions relating to the contract
III.1.1)Deposits and guarantees required:
The Contracting Authority may require guarantees or other security acceptable to the Contracting Authority from tenderers. To be detailed in the Invitation to Tender.
III.1.2)Main financing conditions and payment arrangements and/or reference to the relevant provisions governing them:
To be detailed in the Invitation to Tender.
III.1.3)Legal form to be taken by the group of economic operators to whom the contract is to be awarded:
Subject to the status and involvement of the parties, the Contracting Authority may require parties to commit to joint and several liability in respect of the Contract. Alternatively, the Contracting Authority may expect the lead operator to take total responsibility. The Contracting Authority may require collateral warranties, parent company
guarantees and / or performance bonds (as applicable) to be entered into by other economic operators.
III.1.4)Other particular conditions
The performance of the contract is subject to particular conditions: yes
Description of particular conditions: As detailed in the contract documentation. The project will be subject to the Association obtaining Planning Approval, Project Approval and grant funding from NIHE (DPG) for the scheme. Under this procurement the contractor is required to participate in fulfilling governmental obligations regarding the promotion of equality of opportunity and sustainable development. The proposed number and type of dwellings may be subject to change upon above approvals.
III.2)Conditions for participation
III.2.1)Personal situation of economic operators, including requirements relating to enrolment on professional or trade registers
Information and formalities necessary for evaluating if the requirements are met: The requirements will be consistent with those permitted under Directive 2004/18/EC and will be detailed in theMemorandum of Information and Pre-qualification Questionnaire.
III.2.2)Economic and financial ability
Information and formalities necessary for evaluating if the requirements are met: The requirements will be consistent with those permitted under Directive 2004/18/EC and will be detailed in the Memorandum of Information and Prequalification Questionnaire.
Minimum level(s) of standards possibly required: The requirements will be consistent with those permitted under Directive 2004/18/EC and will be detailed in the Memorandum of Information and Prequalification Questionnaire.
III.2.3)Technical capacity
Information and formalities necessary for evaluating if the requirements are met:
The requirements will be consistent with those permitted under Directive 2004/18/EC and will be detailed in the Memorandum of Information and Prequalification Questionnaire.
Minimum level(s) of standards possibly required:
The requirements will be consistent with those permitted under Directive 2004/18/EC and will be detailed in the Memorandum of Information and Prequalification Questionnaire. applicants are subject to the Buildsafe NI initiative.
III.2.4)Information about reserved contracts
III.3)Conditions specific to services contracts
III.3.1)Information about a particular profession
III.3.2)Staff responsible for the execution of the service

Section IV: Procedure

IV.1)Type of procedure
IV.1.1)Type of procedure
Restricted
IV.1.2)Limitations on the number of operators who will be invited to tender or to participate
Envisaged number of operators: 6
Objective criteria for choosing the limited number of candidates: In accordance with Regulation 16, the minimum number of economic operators shall not be less than 5. The envisaged number of operators is currently 6.
IV.1.3)Reduction of the number of operators during the negotiation or dialogue
IV.2)Award criteria
IV.2.1)Award criteria
Lowest price
IV.2.2)Information about electronic auction
An electronic auction will be used: no
IV.3)Administrative information
IV.3.1)File reference number attributed by the contracting authority:
Minor Works Multi Lot.
IV.3.2)Previous publication(s) concerning the same contract
no
IV.3.3)Conditions for obtaining specifications and additional documents or descriptive document
IV.3.4)Time limit for receipt of tenders or requests to participate
1.2.2013 – 15:00
IV.3.5)Date of dispatch of invitations to tender or to participate to selected candidates
IV.3.6)Language(s) in which tenders or requests to participate may be drawn up
English.
IV.3.7)Minimum time frame during which the tenderer must maintain the tender
IV.3.8)Conditions for opening of tenders

Section VI: Complementary information

VI.1)Information about recurrence
This is a recurrent procurement: no
VI.2)Information about European Union funds
The contract is related to a project and/or programme financed by European Union funds: no
VI.3)Additional information
The cost of responding to the prequalification questionnaire package (PQQP) and any subsequent invitation to tender and participation in the procurement process generally will be borne solely by each economic operator participating. A Memorandum of Information and pre-qualification questionnaire package (PQQP) is available in respect of the project referred to in Section I above. Economic operators should note that the Contracting Authority reserves the right to cancel this procurement process at any stage. Any expenditure, work or effort undertaken prior to the contract award is at the sole risk of the economic operator participating in this procurement process. All discussion and correspondence will be deemed strictly “subject to contract” until a formal contract is entered into. The formal contract shall not be binding until it has been signed and dated by the duly authorized representatives of the parties. Any date given in Section IV above is a best estimate at the time of despatch. The Contracting Authority, reserves the right to extend any such date. Further to Section IV.1.2 above, and for the avoidance of doubt the number of Economic Operators who will be invited to tender will be restricted to [6] Economic Operators. The estimated value of the works contract to which this notice relates falls below the relevant financial threshold under Directive 2004/18/EC (as amended). Neither the publication of this Notice nor the employment of any particular terminology or any other indication shall be taken to mean that the contracting authority intends to hold itself bound by Directive 2004/18/EC (as amended) as implemented by the Public Contracts Regulations 2006 (as amended).
VI.4)Procedures for appeal
VI.4.1)Body responsible for appeal procedures
VI.4.2)Lodging of appeals
VI.4.3)Service from which information about the lodging of appeals may be obtained
VI.5)Date of dispatch of this notice:
23.1.2013

Enjoyed this post? Share it!